In 2017, the silviculture activity has successfully treated about 10,720 hectares within the USM SFMP area which involved 19 compartments (Table 1). Various sources of funds were involved to support silviculture treatment i.e. The Heart of Borneo (HoB) Initiative project under the Federal 11th Malaysian Plan at the Ulu Segama Forest Reserve and Virgin Jungle Reserve Sepagaya; and WWF-Malaysia and Community Forestry Projects at the Bukit Piton Forest Reserve. Since 2006, a total about 54,976 ha of forest reserves were silviculture treated within the USM SFMP (Figure 1).

No. Compartments Achievement (ha) Funded by
1. 110 410 PPM Fund
2. 111 25 WWF (Malaysia) Fund
3. 153 561 HoB Fund (RMK 11)
4. 154 500
5. 155 326
6. 156 671
7. 157 504
8. 169 562
9. 171 371
10. 172 597
11. 174 682
12. 175 493
13. 177 595
14. 178 467
15. 189 132
16. 167 840
17. 168 752
18. 225 803
19. 226 1,429
  Total: 10,720  



Figure 1:
 
Accumulated silviculture treatment area since 2006

Five permanent Sample Plot (PSP) plots were established since 2010 in different locations as shown in Figure 2. In 2016, mean diameter increment for dipterocarp and non-dipterocarp has increased to 0.4cm and 1.17cm respectively.


Figure 2:
 Mean annual diameter increment as of 2016


Silviculture area under the HoB Fund (RMK11) in 2017

 


Silviculture treatment at Cpt 155 and Cpt 156, Ulu Segama Forest Reserves

 


Silviculture treatment at Cpt.225, Virgin Jungle Reserve Sepagaya


Silviculture treatment in Bukit Piton Forest Reserve

 


Before and after silviculture treatment at compartment 110, Bukit Piton Forest Reserves

 

Silviculture treatment done in the year :
| 2006, 2007 & 2008 | 2009 & 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019