REHABILITATION IN 2012
2012
The initial target for planting was 1,280 hectares. However, toward the end of 2012, the actual planted or restored area is 1,501 hectares or about 17% of the total planted exceeded from the original target. The planting achievement is shown in table as follows:
No. | Location | Compt.# | Target Area (ha) | Achievement (ha) | Contractor | Funded By |
1. | Bt Piton FR | 105 | 100 | 85.48 | Kontraktor Malaysia | YS |
2. | Bt Piton FR | 106 | 250 | 182.44 | Yayasan Sabah | YS |
3. | Bt Piton FR | 121 | 45 | 0 | - | SFD (D11 vote) |
4. | Bt Piton FR | 109 | 200 | 221.94 | AlamBina Flora | WWF (Malaysia) |
45 | 68.72 | Syt. Juta Jaya | WWF (Malaysia) | |||
0 | 17.80 | Sulai-Sulaian Ent. | WWF (Malaysia) | |||
5. | Bt Piton FR | 110 | 50 | 126.10 | Kontraktor Malaysia | WWF (Malaysia) |
35 | 73.20 | Impian Jaya | WWF (Malaysia) | |||
50 | 103.30 | Segama Forest Heritage Ent. | WWF (Malaysia) | |||
6. | Bt Piton FR | 111 | 50 | 36.54 | PertanianKondowoi | WWF (Malaysia) |
7. | Bt Piton FR | 113 | 400 | 517.98 | Emas Jaya Ent. and SFD | Yayasan Sime Darby |
114 | 300 | 289.66 | ||||
TOTAL : | 1,280 | 1,501.22 | (117%) |
While for maintenance activity, about 5,173 hectares were archived surpassing the initial target of 2,550 hectares. The maintenance achievement is shown in table as follows:
No. | Location | Compt.# | Target Area (ha) | Achievement (ha) | Contractor | Funded By |
1. | Bt Piton FR | 105 | 50 | 297.52 | Kontraktor Malaysia | YS |
2. | Bt Piton FR | 106 | 200 | 293.54 | YS | YS |
3. | Bt Piton FR | 107 | 250 | 173.69 | Kontraktor Malaysia | YS |
4. | Bt Piton FR | 109 | 300 | 721.08 | AlamBina Flora | WWF (Malaysia) |
30 | 0 | PertanianKondowoi | WWF (Malaysia) | |||
75 | 359.36 | Syt. Juta Jaya | WWF (Malaysia) | |||
40 | 148.36 | Sulai-Sulaian Ent. | WWF (Malaysia) | |||
5. | Bt Piton FR | 110 | 300 | 1,276.38 | Kontraktor Malaysia | WWF (Malaysia) |
100 | 206.51 | Impian Jaya | WWF (Malaysia) | |||
100 | 125.59 | Segama Forest Heritage Ent. | WWF (Malaysia) | |||
6. | Bt Piton FR | 111 | 100 | 145.92 | PertanianKondowoi | WWF (Malaysia) |
7. | Bt Piton FR | 112 | 500 | 951.34 | AY Ent. | Yayasan Sime Darby |
113 | 200 | 11.98 | ||||
114 | 200 | 302.26 | ||||
116 | 25 | 62.74 | ||||
8. | VJR Merisuli | 121 | 80 | 97.21 | Kontraktor Malaysia | SFD |
TOTAL : | 2,550 | 5,173.48 | (203%) |
Map : Restored forest within project area for the period of 2007 tp 2012
Summary Analysis for Monitoring Programme in 2012
Based on the preliminary analysis of monitoring programme undertaken in various forest restoration activities within the Ulu Segama Malua SFM Project area, it revealed that the mean mortality rate is about 12.6% (as shown in Table below). The mortality of planted seedlings were contributed by several factors such quality of seedlings, water stress during prolonged drought, weeds competition, wildlife disturbance and human carelessness (poor planting technique and planting material handling).
NO. | CPT# | RESTORED AREA (HA) | MORTALITY RATE (%) | NOTE |
1. | 105 | 263.00 | 6 | 20% census |
2. | 107 | 751.00 | 9 | 20% census |
3. | 109 | 718.00 | 10 | 20% census |
4. | 110 | 592.00 | 14 | 20% census |
5. | 111 | 187.00 | 5 | 20% census |
6. | 112 | 551.00 | 21 | 100% census |
7. | 114 | 309.00 | 17 | 100% census |
8. | 116 | 33.00 | 22 | 100% census |
9. | 121 | 324.00 | 17 | 20% census |
10 | Infapro | 11,827.00 | 5 | 100% census |
TOTAL : | 15,555.00 | |||
Mean Mortality (%) | 12.6 |
Rehabilitation achievements for year : 2008, 2009 & 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017